Data center site management, logistics and procurement

In brief

Site management is at the core of what Finkova does. We coordinate trades, schedule and safety, and run internal logistics and procurement, so systems are completed in the right order and handed over fully documented. Finkova's current data center work already includes all three.

Delivery scope

  • Coordination of daily installation work, work areas and contractor interfaces within the agreed mandate.
  • Internal logistics, equipment movements and material availability for the installation sequence.
  • Procurement coordination, delivery tracking and material planning against the project schedule.
  • Progress reporting, issue tracking and preparation for inspections and handover.
  • Support for the owner's own team during construction and after handover.

Responsibilities and interfaces

The client, the principal contractor and Finkova agree authority, reporting lines and safety responsibilities. Procurement is coordinated with the client's approved suppliers and purchasing arrangements.

A schedule that holds

In process industry, shutdowns are measured in hours. Finkova brings a data center live with the same discipline: scope splits written down before the tender documents go out, cleanliness responsibility assigned before the first flush, and commissioning protected from being squeezed at the end of the programme.

What to send us

Send the site programme, work packages, organisation chart, logistics constraints, procurement responsibilities and the required mobilisation date.

Frequently asked questions

What does site management cover on a data center project?

Coordination of trades, schedule and safety, internal logistics and procurement, progress reporting and preparation for inspections and handover, within the mandate agreed with the client and the principal contractor.

Why does commissioning get squeezed, and how is it prevented?

Commissioning comes last, so installation delays eat into it, and the cut usually lands on flushing and fault scenario testing. Protecting it starts in the programme: test stages, sign-offs and responsibilities are agreed before work begins.

Discuss the delivery scope

Send the project inputs listed above, or call us to define responsibilities, schedule and next steps.

All contacts

Ville Keltikangas

Data center solutions

Ville Keltikangas

+358 40 704 2514

ville.keltikangas@finkova.fi

More about cookies

Finkova Oy uses Google Analytics (Google) for page views, traffic sources and interaction counts. Google processes usage and device data. Processing may take place outside the EEA. Analytics cookies (_ga and _ga_*) last up to 180 days. Google advertising features are disabled in this implementation.

Your choice is stored in this browser for 180 days (localStorage: finkova-consent-v2). You can change it at any time through Cookie settings in the footer. Withdrawal stops future collection and removes this site’s analytics cookies. The form cookie finkova_form expires at the end of the browser session.

Microsoft Clarity processes interaction and device data to provide heatmaps and session recordings. Its _clck and _clsk cookies connect visits and page views. Microsoft may process data outside the EEA. Advertising storage consent is denied. Cookie details and Microsoft privacy information are linked below.

Finkova privacy notice

Microsoft privacy statement · Clarity cookies

Google privacy policy · Contact Finkova about privacy